Construction of the terminal and pumping stations of Bandar Abbas / Sirjan / Rafsanjan new 26-inch pipeline for the transfer of gasoline, kerosene and diesel oil from the Persian Gulf Star refinery to the central regions of the country
Job Description
- Construction of a new pumping station in Bandar Abbas for the 26-inch pipeline with a capacity of 300,000 barrels per day
- Construction of a new pumping station in Qotbabad for the 26-inch pipeline with a capacity of 300,000 barrels per day
- Construction of a new pumping station in Mehraran for the 26-inch pipeline with a capacity of 300,000 barrels per day
- Construction of a new terminal in Rafsanjan for the 26-inch pipeline with a capacity of 300,000 barrels per day
- Construction of a new terminal in Sirjan for the 8-inch pipeline with a capacity of 35,000 barrels per day
- Engineering (E): Preparation of documents and technical specifications, procurement engineering, documents and maps required for project implementation and commissioning: 1,900 documents
- Purchase and procurement of goods and materials (P): 61 items
- Executive operations (C):
- Supply and installation of 18 electric pumps and 3 diesel devices each with an electric power of about 4 MW
- Supply and installation of variable-frequency drive (VFD) systems for an increase in energy efficiency
- Design and installation of leak detection system (LDS) for 459 km of the 26-inch pipeline
Title Capital
In Local Currency: 1,520 billion Rials