Goals
- Reconstruction of 6 piers and dredging for mooring ships of 30,000 to 80,000 tons
- Increase in loading and unloading capacity of petroleum products from 50,000 tons to 90,000 tons
- Construction of 17 new storage tanks and renovation of 28 existing storage tanks and increase of storage volume by 3 million and 500 thousand barrels
- Adding equipment for exporting fuel oil, kerosene, diesel oil, gasoline, etc. (totally from 50,000 tons to 90,000 tons)
- Equipment of new piers with advanced control systems
- Adding equipment for importing gasoline, MTBE and diesel oil
- Adding equipment to export various types of ship fuels
- Updating the existing facilities
Job Description
- Construction of tanks and reconstruction of piers and renovation of worn-out equipment of Mahshahr export port in order to increase productivity and meet the growing need for export and import of petroleum products from Mahshahr export port
Onshore Sector:
- Engineering (E): Preparation of documents and technical specifications, procurement engineering, documents and maps required for project implementation and commissioning: 4,082 documents
- Purchase and procurement of goods and materials (P): 80 items
- Executive operations (C):
o Excavation operations: 2,400,000 cubic meters
o Steel reinforcement: 2,000 tons
o Formwork: 95,000 square meters
o Concreting: 23,000 cubic meters
o Piping: 103,000 meters
o Welding: 370,000 inches in diameter
o Construction of 17 new storage tanks with a total capacity of 557 million liters
o Construction of surface water conduction channels with a length of 12,000 meters
o Construction of industrial and non-industrial buildings: 6,500 square meters
o Road construction: 17 km
o Electrical cabling: 694 km
o Construction of 132 and 33 kV double circuit transmission lines with a length of 17 km
o Construction of 132 to 133 kV main electrical substation and development of 132 kV Dobi in 400 kV substation of Mahshahr and the export port
Offshore Sector:
- Engineering (E): Preparation of documents and technical specifications, procurement engineering, documents and maps required for project implementation and commissioning: 2,180 documents
- Purchase and procurement of goods and materials (P): 33 items
- Executive operations (C):
o Demolition and construction of 6 new piers
o In-situ concrete: 18,000 cubic meters
o Centrifuge piling: 22,000 meters
o Metal piling: 3,000 meters
o Piping: 53,500 meters
o Dredging: 2 million cubic meters