Project Title Construction Project of Abadan / Shazand / Qom / Rey Petroleum Products Pipeline
Goals - Increase in transfer capacity of petroleum products from Abadan to Nezamiyeh in Ahvaz up to 250,000 barrels per day - Increase in transfer capacity of petroleum products from Shazand to Rey up to 300,000 barrels per day
Job Description Construction of a 26-inch pipeline from Abadan oil refinery to Nezamiyeh of Ahvaz, and from Shazand of Arak to Tehran with a length of 428 km Construction of a pipeline from Abadan to Nezamiyeh of Ahvaz with a capacity of 250,000 barrels per day Construction of a pipeline from Shazand to Rey with a capacity of 300,000 barrels per day Construction of the equipment required in Shazand, Qom and Rey stations for operation
Title Capital Rial Capital: 3,800 billion Rials

Foreign Capital:
Employer NIOEC
Project Managment NIOEC
Contractors Khatam al-Anbiya Construction Headquarters - Energy Development Specialized Group
Consultant Tarh-e-now Andishan Consulting Engineering Co.
Contract Type EPC