Goals
- Renovation, reorganization and updating of crude oil receiving facilities, transfer of fuel oil and receipt and transfer of Abadan refinery petroleum products
Job Description
- Construction of a 16-inch pumping station (Unit 201) for the transfer of products from Abadan to Ahvaz with a capacity of 140,000 barrels per day
- Construction of a 12-inch pumping station (Unit 202) for the transfer of products from Abadan to Ahvaz with a capacity of 50,000 barrels per day
- Construction of a 16-inch pumping station (Unit 203) for the transfer of products from Abadan to Mahshahr with a capacity of 106,500 barrels per day
- Construction of a 16-inch pumping station (Unit 204) for the transfer of ORD from Abadan to Mahshahr with a capacity of 130,000 barrels per day
- Construction of a 16-inch pumping station (Unit 204) for the transfer of ORD from Abadan to Mahshahr with a capacity of 130,000 barrels per day
- Construction of a 26-inch pumping station (Unit 206) for the transfer of fuel oil from Abadan to Mahshahr with a capacity of 250,000 barrels per day
- Construction of a 16-inch terminal (Unit 203) for the receipt of products from Mahshahr with a capacity of 106,500 barrels per day
- Construction of a 16-inch terminal (Unit 210) for the receipt of crude oil from Darkhovin with a capacity of 110,000 barrels per day
- Construction of a 24-inch terminal (Unit 208) for the receipt of crude oil from 40 miles of Mahshahr with a capacity of 210,000 barrels per day
- Design, reorganization and implementation of communication pipelines of pumping stations and terminals inside Abadan oil refinery with a length of approximately 2 km
- Engineering (E): Preparation of documents and technical specifications, procurement engineering, documents and maps required for project implementation and commissioning: 2,298 documents
- Purchase and procurement of goods and materials (P): Procurement of 92 packages
- Executive operations (C):
- Pile construction and piling: 48,464 meters
- Road construction: 2,000 meters
- Piping: 2,000 meters
- Disposal of contaminated soils: 47,500 cubic meters
- Backfilling and land leveling: 66,000 cubic meters
Title Capital
In Local Currency: 4,320 billion Rials
In Foreign Currency: € 21 million