Implementation of the Project to Renovate and Increase Capacity of Abadan Oil Refinery (First Phase)

- Construction process from 2003 to 2010 - Construction of a new refinery with a capacity of 180,000 barrels per day - Maintenance of the refining capacity of 360,000 barrels per day by constructing new units and dismantling the old ones - Maximum increase in gasoline production and improvement in the quality of middle distillates - Production of products with modern technology based on Euro 5 standard and reduction in environmental pollutants - Supply of feed for downstream industries (Bandar Imam Petrochemical Company, oil and asphalt manufacturing factory) - Construction of new storage tanks and collection of 13 old worn-out tanks

Last Update Page: 11/8/2023